April 2023 FAQs

Last Update 4/6/2023

How much more is the estimate from the total amount appropriated to the project at referendum? 

The estimate completed at the end of Design Development is $72.6 million, $14 million over the appropriated amount at the referendum. This figure includes $835K cost of delay due to the project currently being paused. These numbers have come down by $5 million since the last estimate and continued to be reviewed by the town, architect and building committee. Cost reductions opportunities will continue to be studied once the project is permitted to proceed again. 

What are the project’s next steps? 

The Town Council will hold a special meeting Thursday, April 6 at 6 p.m. to discuss the next steps of the project. The Town Manager has also been meeting with the town’s bond counsel and attorney and will provide more information. The project is currently paused and no work by the construction manager and architect can take place. 

When was the Building Committee provided the Design Development estimate?

The Design Development estimate was provided to the Building Committee at its April 5 meeting. The meeting is  available for viewing on the committee’s YouTube channel.

Why is the project over budget? 

At this time the project is not over budget. All expenses encumbered by the project are within the allocated amounts in the project budget. This includes the costs paid to the Architect and Project Manager as well as the contract costs for the Construction Manager and Commissioning Agent. 


The estimate indicates that the project is currently at risk to go over the total construction budget if all current assumptions and risks come to fruition.  Since these risks are very likely, it is prudent to review all project options and meet with the Town Council and Board of Finance to determine the next steps.

What has been done to address the increased estimate?

The committee has implemented many cost savings initiatives into the project since the Schematic Design estimate. As the committee enters the next phase of the project, it will continue to review the most cost effective options for the construction. 

Is the estimate the final number? 

No.  There will be one more estimate completed before construction begins near the end of the construction documentation phase. The town and committee will not know the final construction numbers until the project goes out to bid and has actual numbers instead of estimates. 

Is Cromwell responsible for the full amount if the project proceeds and goes over the referendum budget?

No.  The State of Connecticut advised that the town’s reimbursement rate (which is currently 39.4% for the school and 19.7% for central office; less ineligibles) will apply to the final total, not the original anticipated budget. This scenario would require additional appropriation through the town’s processes. 

Can a school be scaled down to build within the budget appropriated at the referendum?

Yes, a school could be built within the budget approved by referendum in June 2022.  That version of a school, however, would not be built to the educational specifications set by the Board of Education and would  likely not include things like sports fields, an auditorium, or improvements to parking. 

Is this problem unique to Cromwell? 

No, this problem is not unique to Cromwell.  All other school building projects at the same point in their project are also facing the same situation. In fact, this problem is not limited to schools as even commercial and real estate projects are burdened by inflation. 

Was an allotment made in the budget to allow for inflation? 

Yes.  The standard contingency for inflation in a school building project is 3%. The Building Committee increased that to 6% in the budget appropriated at referendum.

What happens if we delay the project for a year?

If the project is delayed by a year, the grant application process with the State of Connecticut would start over again.  This impacts: 

What if plans are changed to renovate the existing school instead?

Changing the scope of the project to a ‘renovate’ or a ‘renovate like new’ will mean starting at the beginning of the process including going back to the state with the grant application.  This would delay the project and include the same challenges as delaying for a year. In addition, a ‘renovate’ or a ‘renovate like new’ is a longer, multi-staged project and each stage is bid out separately after completion of the previous stage.  Extending the total project timeline increases the project’s risk to the volatile construction market. 


In addition, a ‘renovate’ would not meet the education specifications set by the Board of Education and fundamental issues such as security and parking would not be resolved. Students will also be impacted as they learn in a school surrounded by construction for an estimated 3 years for a ‘renovate like new’ project or estimated 4 to 5 years for a ‘renovate’ project.

What is the tax impact for this additional appropriation

The original estimated tax impact for the $58.6M appropriation that passed in May 2022 can be found here. 

At this time the Board of Finance has not provided the estimated tax impact for the additional appropriation of $13,995,600. 

Where can I get additional information?

Questions and comments can be emailed to CMSBuildingCommittee@gmail.com