Student Information Management System Project Documentation with PHP source code

Student Management system C# .Net Project is designed to deal with all kinds of student details ranging from academic reports, college information.

PROJECT SOURCE CODE

STUDENT INFORMATION SYSTEM PROJECT SOURCE CODE

PROJECT REPORT

SPONSORED LINKS

STUDENT INFORMATION SYSTEM PROJECT REPORT

ONLINE UNIVERSITY STUDENT ADMISSION SYSTEM PROJECT SOURCE CODE

ONLINE STUDENT ADMISSION MANAGEMENT SYSTEM PROJECT REPORT

COMPLETE ONLINE ADMISSION MANAGEMENT SYSTEM PROJECT WITH REPORT AND SOURCE CODE

FREE DOWNLOAD ALL THE PROJECT REPORTS WITH SOURCE CODE FROM HERE

OTHER PROJECTS YOU SHOULD REVIEW

8. GENERAL STORE BILLING SYSTEM PROJECT

9. CUSTOMER CARE MANAGEMENT SYSTEM PROJECT IN ASP NET

10. HOSPITAL MANAGEMENT SYSTEM PROJECT

Student Information System Online Student Management System / the future implementation will be online help for the users to obtain information. Project For a given set of requirements it is desirable to know how much it will cost to develop the software to satisfy the given requirements, and how much time development will take. These estimate are needed before development is initiated .The primary reason for cost and schedule estimation is to enable client or developer to perform a cost benefit analysis and for project monitoring and control . Software :Student academic Management system Project, Supported Languages:Asp.Net ,Vb.Net, The student academic management system. A more practical use of these estimates is in bidding for software projects, where the developers must give cost estimates to a potential client for the development contract. For a software development project, detailed and accurate cost and schedule estimate are essential prerequisites for managing the project. Download Student Information System in JAVA Source Code Similar Projects: Student Database Management System (Computer Project). Otherwise, even simple question like “Is the project late”, “Are there cost overruns”, and “when is the project likely to complete” cannot be answered. Cost and schedule estimate are also required to determined the staffing level for a project a deferent phase. it can be safely said that cost and schedule estimates are fundamentals to any form of management and are generally always required for a project. A student information system (SIS) Maintenance boarding house details or Hostel/Dorm Management; Communicating student details to parents through. Cost in a project is due to requirement for software, hardware, and human resources. Hardware resources are such things as the computer time, terminal time and memory required, whereas software resources include the tool and compiler needed during development. The bulk of the cost of software development is due to human resources needed, and most cost estimation procedure focus on this aspect. STUDENT INFORMATION MANAGEMENT SYSTEM PROJECT REPORT Most cost estimates are determine in terms of person-month(PM). that Washington State University provide contemporary information management systems that will The Student Information System project is a key component. By properly including the “Overheads” in rupees cost of a person-month , beside including the direct cost of the person month ,most cost for a project can be incorporated by using PM as the basic measure. Estimates can be based on subjective opinion of some person or determined through the use of models.TOPIC Page No: 1. INTRODUCTION 1 Management Information System Student Information Management System 2. PROBLEM DEFINITION 3 3. OBJECTIVE. The estimation of cost of the project is a difficult task but we can estimate the cost of the project by various methods. I am using the COCOMO (Constructive Cost Model).

The model has following hierarchy:-

Model 1:- The basic COCOMO model computed software development effort land cost as a function of program size expressed in estimate lines of code.The main objective of developing this Student Management System final year .Net project is to provide create efficient software for managing students in schools. STUDENT INFORMATION MANAGEMENT SYSTEM PROJECT REPORT REVIEW The intermediate COCOMO model computer software development effort as a function of program size and a set of “cost drivers” that include subjective assessments of product, hardware personal and project attributes.A Student Management System (SMS) is designed to help collages for management of dental student. Extensive information is available at your fingertips. The advance COCOMO model incorporate all characteristics of the intermediate version with an assessment of the cost drivers impact on each step (analysis, design etc.) of software engineering process.

The COCOMO models are defined for three classes of software projects are:-

1) Organic Mode:- Relatively small, simple projects in which small team with application experience work to a set of less than rigid requirements.Project Report on Student Information Management System. 2)Semidetached Mode:- An intermediate(in size and complexity)software project in which teams with mixed experience levels must meet a mix of rigid and less than rigid requirements.

Report on Student Information Management . A software project that must developed within a set of tight hardware ,software and operational constraints.

The basic COCOMO equation takes the form.

E = ab KLOCbb

D = CbEdb

When E is the effort applied in person months, D is the development time in chronological month KLOC is the estimated number of delivered lines of code for the project.(Express in thousands).The coefficients ab and cb and the exponent bb and db where taken as . PROJECT Student information management system.

The project is an organic project so :-

ab = 2.4

bb = 1.05

cb = 2.5

db = 0.38

LOC = 1555

KLOC = 1555/1000 =1.555

E = 2.4(KLOC)1.05

= 2.4(1.555)1.05

= 3.84

= 4 person-month

Now calculate the D is the development time in chronological months

D = 2.5 E0.35

= 2.5(4)0.35

= 4.06 months

= 4 months approximately

the computer project duration we use the effort estimated described above

N = E/D

= 4/4

= 1 person

when N is the recommended number of people for the project.